TELECITY Data Center Phases 2 & 3
Location: Skondal – Stockholm, Sweden
Client: Telecity Group AB
Project Managers: Telecity Group
Consultant: CTS (Turn-Key M&E) + MEIT Phase 3
Duration: 9 months | Aug 09 to April 10 Phase 2 | July 11 to October 11 Phase 3
Value: EUR €26 Million (Phase 2 €20 Million | Phase 3 €6 Million)
Scope:
- Turn-key. Complete DC project including some construction works & the entire fit-out.
- Design, procurement, installation, testing, balancing & commissioning of HVAC / Mechanical & all Electrical systems for approximately 2500 m² Data Center.
- 9 MW facility, including Generators, UPS’s, PDU’s
- 4 x 1.3 MW Chillers + associated CHW CRAC units